1. Purpose and application
These Construction & Project Terms ("Build Terms") apply to construction, renovation, civil works, interiors, project management, material procurement, contractor-managed projects and other large or multi-stage assignments booked through Obrero Build or Obrero Pro. They supplement the Customer Terms. For a project governed by a separate Work Order, BOQ, Scope of Work, quotation, project schedule or project agreement, those documents form an integral part of the contractual arrangement.
A ₹500 repair visit and a large renovation contract do not operate under the same terms: larger projects are governed by these Build Terms plus a project-specific Service Order / Project Agreement containing the scope, price, milestones, materials, warranty, completion criteria and payment schedule.
2. Project contract documents
Each project may consist of: Master Project Agreement; Scope of Work (SOW); Bill of Quantities (BOQ); approved drawings/specifications; material schedule; project quotation; payment/milestone schedule; project timeline; Change Orders; Site Readiness Checklist; inspection records; snag/punch list; Completion/Handover Certificate; and the applicable warranty/DLP schedule. Together these constitute the Project Contract. Where documents conflict, the more specific project document generally prevails, subject to applicable law.
3. Project delivery model
The Project Contract identifies the commercial model:
- Lump-sum / fixed-price — the agreed scope and quantities are priced for the agreed amount, subject to approved variations and identified exclusions.
- Item-rate — payment = actual approved quantity × contracted unit rate.
- Time & materials — payment based on documented labour, materials, equipment, approved expenses and agreed overhead/profit.
- Hybrid — a combination, disclosed in the Project Contract.
4. Bill of Quantities (BOQ)
The BOQ is the principal commercial document for quantity-based pricing. It identifies, where applicable, item, description, unit, estimated quantity, rate and amount, plus included items, excluded items, assumptions, specifications, brands, taxes, labour, material components and provisional items.
5. BOQ quantities are estimates unless fixed
Unless expressly stated as a fixed-quantity/lump-sum commitment, BOQ quantities may be estimates and may change because of actual site measurements, approved design changes, structural or concealed conditions, engineering or regulatory requirements, or customer-requested changes. No material increase in project cost will be imposed through an undisclosed variation.
6. Quantity variation
- Item-rate projects: the contract unit rate ordinarily applies to the actual approved quantity.
- Fixed-price projects: quantity variation does not automatically change the price where the contractor accepted quantity risk.
- Material variation: where a variation materially changes cost, scope or timeline, a Change Order may be issued before execution.
- No hidden escalation: a Customer will not be presented with a materially higher final invoice merely because an internal estimate was inaccurate, where the contractor assumed that estimation risk.
7. Measurement methodology
The Project Contract specifies the measurement methodology, which may reference applicable Indian Standards (such as IS 1200 where expressly incorporated), project specifications or drawings.
8. Digital measurement record
Obrero may maintain a digital measurement record containing photographs, videos, GPS/location information, timestamps, measurements, worker identity, material records, daily progress, approved quantities, customer approvals and related invoices, recorded against the relevant BOQ item where possible. Digital records are evidence — not an automatic determination of legal liability.
9. Measurement disputes
If a measurement is disputed: the item is identified; photographs and records are reviewed; a remeasurement is conducted where reasonably necessary; the agreed methodology is applied; and the revised quantity is recorded digitally. No party is required to accept an obviously disputed measurement merely because it has been entered into the Platform.
10. Change Orders
A Change Order is a documented change to scope, design, quantity, specification, material, price, timeline or execution methodology. It may arise from customer requests, unforeseen site conditions, engineering requirements, material unavailability, regulatory or safety requirements, or mutually agreed improvements.
11. Digital Change-Order process
Issue identified → Change event → Cost impact → Schedule impact → Customer approval → Execution. A Change Order identifies the original scope, proposed change, reason, quantity change, labour and material impact, revised price, tax impact, timeline impact and approval status.
12. No retroactive billing
A contractor must not perform materially additional chargeable work and then demand payment on the basis of an alleged verbal agreement. Written/digital approval should be obtained before execution wherever reasonably practicable. Emergency work necessary to prevent imminent damage or danger is an exception, but must be documented promptly.
13. Customer-requested design changes
Customer-requested changes may affect project value, procurement, manufacturing, labour, sequencing, other contractors and the completion date. Any such impact will be disclosed before approval, and may result in a corresponding timeline extension where the change genuinely affects the critical path.
14. Contractor-requested variations
Where the contractor requests a variation because of an unforeseen Site condition, it must provide evidence of the condition, why it was not reasonably foreseeable, the proposed remedy, and the cost and schedule impact. Ordinary foreseeable requirements must not be classified as "unforeseen" to increase project value.
15. Site readiness
The Customer must provide a reasonably ready Site before the relevant stage begins. Depending on the project this may require possession of premises; access permissions; electricity; water; working access; lift availability; storage area; removal of personal belongings; structural readiness; completed civil work; approved drawings; building-management permissions; and other project-specific requirements. A Site Readiness Checklist will be provided.
16. Effect of Site non-readiness
Where Site conditions prevent or obstruct execution, affected work may be rescheduled, the timeline may be extended, additional documented costs may apply where contractually permitted, and contractor delay liability does not accrue for the period genuinely caused by non-readiness. Minor inconvenience or ordinary coordination issues do not automatically eliminate a timeline commitment.
17. Customer-supplied materials
If the Customer supplies materials, the Customer bears responsibility for procurement, authenticity, delivery, storage, compatibility, quantity and manufacturer warranty. The contractor remains responsible for workmanship, and must notify the Customer rather than knowingly incorporate a material that is visibly unsuitable or unsafe.
18. Obrero / contractor-supplied materials
The Project Contract identifies product, brand/specification, quantity, unit price, taxes, delivery, warranty, replacement procedure and exclusions. The party responsible for procurement generally bears the corresponding procurement risk.
19. Material inspection at delivery
Customers should inspect delivered materials, where reasonably practicable, for visible damage, quantity, obvious defects, incorrect products, incorrect dimensions and packaging damage, and record any discrepancy promptly through the Platform, preferably with photographs before installation.
20. Latent material defects
Failure to identify a defect that could not reasonably have been detected through ordinary inspection does not eliminate a legitimate latent-defect claim. Latent defects may be assessed based on specifications, manufacturer documentation, photographs, technical inspection, laboratory testing where necessary, installation records and other evidence.
21. Material quality disputes
Obrero may arrange internal, manufacturer or third-party technical inspection, or independent laboratory testing where technically necessary. Testing cost may initially be allocated per the Project Contract and ultimately adjusted according to responsibility or applicable law.
22. Material alteration and acceptance
Customers should inspect materials before cutting, drilling, painting, fabrication, installation or irreversible modification where reasonably practicable. Irreversible use does not eliminate a claim concerning a defect that could not reasonably have been discovered beforehand.
23. Material supply — responsibility matrix
Every material order identifies a Supply Mode: Obrero supplied, partner/seller supplied, customer supplied, or customer-approved third-party procurement. Default responsibility:
| Situation | Default responsibility |
|---|---|
| Wrong material supplied by Obrero | Obrero |
| Short quantity supplied by Obrero | Obrero |
| Visible damage before delivery while Obrero controls logistics | Obrero / logistics partner |
| Defective Obrero-supplied material | Obrero-facing resolution, then supplier/OEM recovery |
| Defective customer-supplied material | Customer, subject to the partner's duty to flag obvious incompatibility or unsafe material |
| Poor workmanship using correct material | Obrero / service partner |
| Customer-approved substitution | Follows the approved substitute/specification |
| Customer changes material after purchase | Customer bears disclosed incremental cost |
| Site not ready for scheduled heavy delivery | Customer may bear reasonable disclosed waiting/demurrage costs |
| Delivery delay caused by Obrero/logistics | Obrero provides the appropriate remedy under the order terms |
| Force majeure | Reasonable rescheduling/EOT, with refund options where appropriate |
| Material consumed/installed | Ordinary return rights may end; quality, warranty and statutory claims do not automatically disappear |
No surprise substitution. Obrero or its supply partner will not substitute a material's brand, grade, specification, size, quantity or technical standard without the customer's recorded approval, unless the customer has expressly authorised an equivalent-substitution mechanism.
Delivery acceptance record. For significant deliveries, Obrero records the order ID, material/brand/specification, ordered and delivered quantity, timestamp, site, photos, visible damage, customer acceptance/rejection, driver/partner details and unloading status. Prices are locked after a confirmed order except for clearly disclosed statutory changes or customer-approved variations; any minimum order quantity is shown before checkout. Returns are category-specific: unused standard goods may be returnable, while consumed, custom or time-sensitive materials (such as ready-mix concrete) may have restricted returns disclosed before purchase.
24. Delivery and site logistics
The Project Contract identifies delivery location and responsibility, unloading, storage, security, access restrictions, transportation, loading/unloading charges and material handling. Risk of loss transfers according to the expressly agreed delivery point and responsibility.
25. Storage
Once materials are delivered, the responsible party takes reasonable measures to protect them against theft, water, weather, unauthorised access, contamination, physical damage and improper storage. If storage is the Customer's responsibility, the Customer will be informed of the storage requirements.
26. Project timeline
The Project Contract specifies planned commencement, estimated duration, target completion, milestone dates, Customer dependencies, material dependencies, Site-readiness conditions and permitted extension events. Unless expressly guaranteed, a project date is a planned contractual target rather than an absolute date unaffected by legitimate variation events.
27. Extension of time (EOT)
An EOT may apply where delay is caused by Customer-requested changes, Customer payment delay, Site non-readiness, delay in Customer-supplied materials, third-party contractor interference, building-management restrictions, government restrictions, force majeure, extraordinary material shortages, concealed structural conditions or another documented event outside the contractor's reasonable control. The contractor must notify the Customer of the delay and estimated impact as soon as reasonably practicable.
28. Contractor delay
Where the contractor causes delay through inadequate manpower, avoidable procurement failures, poor scheduling, repeated no-shows, failure to coordinate subcontractors, avoidable rework or other matters within its control, the contractor remains responsible for the contractual consequences.
29. Delay compensation
Where a project provides for delay compensation, the Project Contract specifies the committed completion date, grace period, compensable delay, calculation, maximum amount (if legally enforceable), excluded delay events and claim procedure. Any delay cap is disclosed before the Customer enters into the Project Contract and is never introduced retrospectively.
30. Weather delays
Ordinary, reasonably foreseeable weather does not automatically excuse delay. Where extraordinary weather materially prevents execution, the contractor may request an EOT with supporting evidence such as weather records, site photographs, daily logs and work-stoppage records.
31. Force majeure
Force majeure covers extraordinary events beyond reasonable control — severe natural disasters, floods, earthquakes, government restrictions, riots, major infrastructure failures, widespread transport disruption, epidemic restrictions or extraordinary strikes. It does not excuse ordinary poor planning, manageable labour shortages, procurement mistakes, cash-flow problems or contractor inefficiency.
32. Daily project log
For larger projects, Obrero may maintain a daily log of workers present, working hours, work performed, quantities, materials delivered, equipment used, photographs, site conditions, weather, delays, instructions, safety incidents and pending decisions — a shared factual record rather than reliance on retrospective statements.
33. Labour and safety
The contractor manages its workforce in accordance with applicable law. Project participants must not use forced labour, child labour prohibited by law, unsafe labour practices or unlawful employment arrangements. Customers must not direct workers to perform clearly unsafe or unlawful activities.
34. Concurrent third-party work
Where another contractor is working at the Site (electrical, plumbing, painting, civil, false ceiling, flooring, furniture, appliance or structural work), the responsible parties must coordinate. Presence of another contractor does not automatically give a complete timeline exemption; the actual impact is assessed.
35. Defect Liability Period (DLP)
Where a DLP is provided, it begins from the agreed Handover/Completion Date unless the Project Contract says otherwise. During the DLP, covered defects attributable to defective workmanship, improper installation, contractor-supplied defective materials or other covered execution failures are addressed in accordance with the Project Contract. The DLP duration (for example 12, 24 or 36 months for specified works) is expressly stated, and different components may have different periods.
36. DLP exclusions
DLP generally does not cover defects caused solely by Customer misuse, unauthorised modifications, third-party repairs, Customer-supplied defective materials, normal wear and tear, accidental damage, vandalism, external infrastructure, extraordinary environmental conditions, failure to follow maintenance instructions or force majeure. An exclusion applies only where the excluded event actually caused the defect.
37. Warranty claims during the DLP
Report a defect through the Platform as soon as reasonably practicable with the project number, location, description, photographs/videos and supporting information. Obrero may inspect before authorising rework.
38. Defect inspection
The party responsible for the original work is not the sole adjudicator of a disputed claim. Obrero may appoint a QA engineer, independent technician, project manager, specialist, manufacturer representative or independent expert to determine: what failed → why it failed → who controlled the cause → what remedy is appropriate.
39. Root-cause analysis
For significant defects, the inspection may examine the original specification, BOQ, material source, installation method, photographs, daily logs, environmental conditions, Customer use, third-party intervention, maintenance records and subsequent modifications — to determine causation rather than automatically assign blame.
40. Punch list / snag list
Before final handover, the Customer and project team may conduct a joint inspection. Each defect or incomplete item is recorded with a description, photograph, location, responsible party, priority, target rectification date and status.
41. Handover
Handover occurs when the contractual scope is sufficiently complete for the Customer to take possession, subject to documented minor snag items where permitted. The Handover Record may include completed scope, outstanding snags, keys/access credentials, manuals, warranties, invoices, material information, photographs, completion date and DLP commencement date.
42. Handover does not extinguish latent-defect rights
Formal handover does not by itself eliminate a valid claim concerning a latent defect that could not reasonably have been identified during handover inspection.
43. Final payment and retention
Where milestone or retention payments apply, the Project Contract specifies amount, due date, milestone, acceptance criteria, retention amount, release conditions and treatment of disputed amounts. A Customer should not withhold an entire undisputed payment because one small item is disputed, and a contractor should not demand payment for materially incomplete or disputed work contrary to the agreed milestone conditions.
44. Suspension for Customer non-payment
If an undisputed payment is not made after the applicable notice period: a reminder is issued; the Customer is given a cure period; execution may be suspended if default continues; documented remobilisation costs may apply where contractually permitted; and the timeline may be adjusted. The contractor must take reasonable steps to mitigate losses.
45. Suspension for contractor default
Where the contractor materially fails to perform, Obrero may issue a corrective notice, allow a reasonable cure period, reassign further work, consider replacement execution and assess applicable refunds/compensation. For serious safety, fraud or abandonment situations, immediate protective action may be taken.
46. Termination
For cause — material breach, persistent non-performance, abandonment, serious safety violation, fraud, repeated unauthorised billing, prolonged non-payment or other material default. For convenience — if permitted, the Project Contract specifies notice, completed-work valuation, material commitments, cancellation charges, refunds, demobilisation, outstanding payments and ownership of purchased materials.
47. Project abandonment
If a contractor abandons the Site without justification, Obrero may document the Site condition, secure project records, assess incomplete scope, obtain replacement quotations, coordinate alternative execution and determine contractual remedies. If the Customer abandons the project, amounts payable are determined based on completed work, committed materials, approved non-cancellable procurement, approved Change Orders, contractual cancellation provisions and applicable law.
48. Procurement cancellation
Material orders may have different cancellation characteristics depending on whether the material has been manufactured, customised, dispatched, delivered, cut, fabricated, installed or procured specifically for the Customer. The Customer will be informed of non-cancellable commitments before approving them wherever reasonably practicable.
49. Digital project record
Obrero may maintain a central record: Booking → BOQ → Quotation → Change Order → Payment → Delivery → Daily log → Inspection → Snag → Handover → Warranty.
50. Digital approvals
Approval may be recorded through app confirmation, OTP, electronic acceptance, WhatsApp confirmation through an authorised channel, email, a digitally signed document or another authorised electronic method. Review scope and price before approving.
51. No verbal promise override
For major projects, material commercial promises must be incorporated into the Project Contract or recorded through an authorised Obrero channel. Marketing statements, informal conversations or verbal representations do not override the written Project Contract unless applicable law requires otherwise.
52. Design and specification responsibility
The Project Contract identifies responsibility for architectural, structural and MEP design, drawings, specifications, material selection, engineering approvals and statutory permissions. Where the Customer supplies a design, the contractor should raise reasonably apparent technical concerns rather than blindly execute a specification with an obvious safety or suitability issue.
53. Customer approval of materials
Where material selection requires approval, the Customer approves brand, colour, model, finish, size, specification and quantity. Once production or irreversible procurement begins, changes may carry disclosed cost and schedule impact.
54. Substitution of materials
If an approved material becomes unavailable, Obrero may propose a disclosed, reasonably comparable alternative, approved where the change is material. A materially inferior substitution will not be made merely to preserve contractor margin.
55. Price escalation
For fixed-price projects, escalation risk is expressly allocated. If escalation is permitted, the contract identifies the affected materials, reference date, mechanism, evidence requirement, maximum adjustment and approval mechanism. No undisclosed escalation is introduced after contract acceptance.
56. Insurance
Where a project is insured, the policy determines covered risks, exclusions, claim procedure, deductibles, limits and documentation. Insurance does not by itself determine legal liability.
57. Construction damage
If property damage occurs, the incident is documented with photographs, date/time, work package, worker identity, material information, site condition and witness information where available, and Obrero may investigate before determining the remedy.
58. Safety stop-work authority
Obrero or the responsible contractor may temporarily stop work where there is a serious and immediate safety risk — exposed live electrical systems, unstable structures, dangerous excavation, gas leakage, unsafe scaffolding, flooding, hazardous materials or other imminent dangers. A safety stoppage is not automatically treated as contractor delay.
59. Customer access and possession
The Customer ensures reasonable Site access during agreed working hours, and communicates building-management rules, security restrictions, access permits and society requirements before commencement.
60. Project communication
For major projects, Obrero may designate a Project Manager, Site Supervisor, Customer Success Manager, QA representative and grievance contact. Use the designated channel for project instructions and disputes.
61. Dispute escalation for Build projects
Level 1 Site/Project Manager → Level 2 Obrero QA / Project Governance → Level 3 Grievance Officer (Grievance Officer (name to be published), obrero.support@gmail.com) → Level 4 Independent expert / mediation → Level 5 Statutory / legal remedy before the competent forum.
62. Five questions for every construction dispute
1. What was agreed? (BOQ / SOW / contract)
2. What changed? (Change Order / site condition)
3. What actually happened? (daily logs / photos / measurements)
4. Who caused the change or failure? (Customer / contractor / supplier / third party / external event)
5. What is the financial consequence? (additional cost / refund / rework / EOT / compensation)
63. Risk allocation
| Risk | Responsible party |
|---|---|
| Customer design change | Customer |
| Contractor workmanship | Contractor; Obrero where contractually responsible |
| Customer-supplied defective material | Customer |
| Obrero-supplied defective material | Obrero; supplier/OEM |
| Contractor procurement delay | Contractor; Obrero where it controls procurement |
| Customer payment delay or site non-readiness | Customer |
| Avoidable contractor delay | Contractor; Obrero where it undertakes delivery |
| Extraordinary force majeure | Shared according to contract |
| Normal wear and tear / unauthorised third-party modification | Customer |
| Latent workmanship defect | Contractor; Obrero where applicable |
| Manufacturing defect | Obrero where it supplied; supplier/OEM |
| Unauthorised additional work | Contractor; Obrero where platform-controlled |
64. The "no surprise" rule
No major scope increase, price increase, material substitution, timeline extension or additional charge should appear for the first time on the final invoice. The Customer will have a reasonable opportunity to see and approve material changes before they become binding, except where immediate action is necessary for safety or prevention of serious damage.
65. The "evidence first" rule
For material disputes Obrero prioritises digital records, then contemporaneous photographs, approved documents, measurements, invoices, and later recollections. No digital record is treated as conclusive where credible evidence shows it is inaccurate or incomplete.
66. Final handover principle
A project is commercially closed after scope completion, snag resolution, documentation, payment reconciliation and warranty/DLP activation. The Handover Certificate identifies any agreed outstanding items.
67. Customer's final project checklist
Before signing final handover, verify: BOQ items completed; measurements verified; materials verified; approved changes completed; electrical points and plumbing checked; water leakage checked; doors/windows, tiles/flooring, paint/finish and fixtures checked; snag list recorded; manuals and warranty documents received; final invoice verified; DLP start date recorded; handover certificate received.
68. Project closeout record
The final project file may contain the approved BOQ, final quantities, Change Orders, invoices, payment history, material invoices, inspection records, photographs, snag list, rectification records, Handover Certificate, warranties, DLP dates and final customer acceptance, retained for the period required by law and Obrero's retention policy.
69. Statutory rights
Nothing in these Build Terms eliminates statutory consumer remedies, waives non-waivable rights, prevents lawful complaints or access to competent consumer forums, or excuses conduct that cannot legally be excluded from liability. Where a provision conflicts with a mandatory legal requirement, the requirement prevails.
70. Governance principle
The party who controls the risk ordinarily bears the risk, and the party who causes the failure ordinarily bears the cost — subject always to the Project Contract and applicable law. Agree → Document → Execute → Measure → Approve changes → Verify → Handover → Protect → Rectify. No hidden scope. No surprise billing. No retroactive liability caps. No automatic blame. No undocumented major changes.